The process of obtaining new printed or online forms for specific Projects is causing delays in overall
Fantastic news! We've Found the answer you've been seeking!
Question:
The process of obtaining new printed or online forms for specific Projects is causing delays in overall project execution. The creation of new forms is outsourced offshore. It can take as long as 3 weeks to receive completed forms/software after the initial request. An initial brainstorming identified 5 potential problem areas.
Requests to Project Team for clarification |
Forms Design Problems |
Forms Development Problems |
Forms Production Problems |
Forms Training & Implementation problems |
These were tracked for the 3 weeks (15 working days) of several new form procurements. The tabulated data is as follows
New Forms | ||||||||||||||||
Potential Problem | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | |
Requests to a project team for clarification | 3 | 5 | 7 | 5 | 8 | 10 | 7 | 6 | 9 | 7 | 5 | 3 | 2 | 7 | 5 | 89 |
Design problems | 2 | 5 | 3 | 2 | 1 | 13 | ||||||||||
Development problems | 2 | 4 | 3 | 5 | 3 | 2 | 1 | 20 | ||||||||
Production problems | 2 | 4 | 3 | 2 | 2 | 1 | 14 | |||||||||
Training and implementation problems | 3 | 3 | 6 | |||||||||||||
3 | 7 | 12 | 8 | 12 | 15 | 10 | 11 | 14 | 13 | 9 | 5 | 4 | 11 | 8 | 142 |
Perform the following analyses of this data. Make logical assumptions as required and document.
- Pareto Chart
- Fishbone is the highest contributing problem. Evaluate the possible impacts of all 6 “M’s”
- Identify the 3 most probable root causes and apply the 5 Why’s to drill down to the most precise definition of the actual root causes.