Question: The product development group at Electronica Telecom has been working on a new software product that has the potential to capture a large segment of

The product development group at Electronica Telecom has been working on a new software product that has the potential to capture a large segment of the market. Through external sources, Telecom's management became aware that the competitor is working on a similar product. Consequently, Telecom's top management increased its pressure on the product development group. The group leader resorted to the PERT/CPM procedure to schedule the remaining activities before the new product can be brought to market.
\table[[,Time in weeks],[Activity,Predecessor,Optimistic (a),Most likely (m),Pessimistic (b)],[A,-,4,8,12],[B,A,6,7,8],[C,A,6,12,18],[D,A,3,5,7],[E,C,D,6,9,18],[F,B,C,5,8,17],[G,E,F,10,15,20],[H,F,G,5,6,13]]
a) Develop a network diagram and identify the critical path activities and duration time.
b) What is the probability that the project will be completed so that Electronica Telecom can launch the new product within 25 weeks? Within 30 weeks?
 The product development group at Electronica Telecom has been working on

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!