Question: The product structure. Bracket LT=Lead time in weeks LT=1 Base(1) Spring(2) LT=1 LT=1 Clamp(1) Housing(2) Clamp(4) LT=1 LT=3 LT=1 Handle (1) Casting(1) Bearing (2) Shaft

The product structure. Bracket LT=Lead time in weeks LT=1 Base(1) Spring(2) LT=1 LT=1 Clamp(1) Housing(2) Clamp(4) LT=1 LT=3 LT=1 Handle (1) Casting(1) Bearing (2) Shaft (1) Handle (1) Casting (1) LT=2 LT=3 LT=1 LT=1 LT=2 LT=3