Question: The product structure diagram for producing item A is given as follows. Gross requirements 60 20 40 30 50 40 90 80 60 100 The
The product structure diagram for producing item A is given as follows.
| Gross requirements | 60 | 20 | 40 | 30 | 50 | 40 | 90 | 80 | 60 | 100 |

The beginning inventory in week 1 for item B and C are 60 units and 90 units respectively. The lead time for both item B and item C is one week. There are 40 units of item B scheduled to be received at the beginning of week 3 and 80 units of item C scheduled to be received at the beginning of week 5.
Suppose A is produced based on the lot-for-lot method, and B and C are produced in batches with a fixed batch size of 100 units and 150 units respectively. Complete the MRP schedule for A, B, and C in the following table.