Question: The product structure for Item X specifies the required number of units for each constituent part within parentheses. (Note that 4 units of part C
The product structure for Item X specifies the required number of units for each constituent part within parentheses. (Note that 4 units of part C are required for X and one unit of part C by B.) The lead times for manufacturing any number of the following components given the the following table:
| Part | Lead Time (in weeks) |
|---|---|
| B | 2 |
| C | 2 |
| D | 2 |
| H | 2 |
| K | 3 |
| M | 2 |
| N | 3 |
| X | 2 |
| Z | 3 |
There is no inventory on hand and the order for Item X is to be shipped at the beginning of week 11. In what week will manufacture of part K start?