Question: The production data has been given for a factory: Units in Process, July 1 1,000 (materials 90% complete, conversion costs 30% complete) Units Started into
The production data has been given for a factory:
| Units in Process, July 1 | 1,000 |
| (materials 90% complete, conversion costs 30% complete) | |
| Units Started into Production | 20,000 |
| Units in Process, July 31 | 2,000 |
| (materials 80% complete, conversion costs 40% complete) | |
| Work in Process on July 1 | |
| Material costs | $1,890 |
| Conversion costs | $987 |
| Cost per Equivalent Unit | |
| Materials | $2.22 |
| Conversion | $3.31 |
Required
What are the costs assigned to units transferred to the next department using the first-in, first-out method (FIFO)?
Step by Step Solution
3.36 Rating (149 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts