Question: The Program Evaluation Review Technique (PERT) and critical path method (CPM) are two techniques that can help you with project management. Which of the following

The Program Evaluation Review Technique (PERT) and critical path method (CPM) are two techniques that can help you with project management. Which of the following statements is true regarding the PERT and CPM? These techniques are normally independent from each other and are not used together. These techniques were introduced in the 1950s by the U.S. government to manage its National Aeronautics and Space Administration (NASA) space programs. The PERT and CPM are two techniques that are normally used together. These techniques are specialized for software projects

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!