Question: The program performance domain that manages the program activities required to facilitate program definition, delivery and closure is the: Select one: a. Program benefits domain

The program performance domain that manages the program activities required to facilitate program definition, delivery and closure is the:

Select one:

a. Program benefits domain

b. Program life cycle management domain

c. Program governance domain

d. Program oversight domain

2.

There are 2 different categories of change in program management: internal and external.

Select one:

True

False

3.

A _________ is a project deliverable that can be delivered by a single accountable person.

Select one:

a. Control unit

b. Work package

c. Work breakdown structure

d. Work task

4.

Which of the following is a cost estimation technique?

Select one:

a. Analogous estimates

b. Top-down estimates

c. Bottom-up estimates

d. All options are correct.

e. Only B and C are correct.

5.The following image is an example of a(n):

Select one:

a. Risk register

b. Communications log

c. Issues log

d. Status matrix

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!