Question: The program performance domain that manages the program activities required to facilitate program definition, delivery and closure is the: Select one: a. Program benefits domain
The program performance domain that manages the program activities required to facilitate program definition, delivery and closure is the:
Select one:
a. Program benefits domain
b. Program life cycle management domain
c. Program governance domain
d. Program oversight domain
2.
There are 2 different categories of change in program management: internal and external.
Select one:
True
False
3.
A _________ is a project deliverable that can be delivered by a single accountable person.
Select one:
a. Control unit
b. Work package
c. Work breakdown structure
d. Work task
4.
Which of the following is a cost estimation technique?
Select one:
a. Analogous estimates
b. Top-down estimates
c. Bottom-up estimates
d. All options are correct.
e. Only B and C are correct.
5.The following image is an example of a(n):
Select one:
a. Risk register
b. Communications log
c. Issues log
d. Status matrix