Question: The project charter for a project was approved for planning, and you have just been assigned as project manager. Realizing that project planning is an

The project charter for a project was approved for planning, and you have just been assigned as project manager. Realizing that project planning is an ongoing effort throughout the project, which processes are you MOST likely to combine?
Estimate Activity Duration and Develop Schedule
Estimate Costs and Determine Budget
Create WBS and Define Activities
Develop HR Plan and Estimate Costs