Question: The Project Charter primarily serves to . . . A . Provide a detailed risk analysis B . Document the final outcomes of the project
The Project Charter primarily serves to
A Provide a detailed risk analysis
B Document the final outcomes of the project
C Serve as a detailed process improvement plan
D Outline the scope, objectives, and stakeholders of the project
E Act as a legal contract between the company and the project team