Question: The project contains 6 tasks. We completed three tasks ( A , B , C ) , and started two ( D , E )

The project contains 6 tasks. We completed three tasks (A, B, C), and started two (D, E) but could not complete them.
The planned budget for each task, Actual cost we spent so far, completion rate by today according to the plan, and actual completion rate by today are shown in the table.
\table[[Task ID,\table[[Planned],[Budget]],Actual Cost,\table[[Planned],[Completion],[Rate by Today]],\table[[Actual],[Completion],[Rate]]],[A,$100,$110,100%,100%
The project contains 6 tasks. We completed three