Question: - The project control process involves all of the following except taking corrective action imemediately if actual performance is behind planned performance. regularly gathering data
The project control process involves all of the following except
taking corrective action imemediately if actual performance is behind planned performance.
regularly gathering data on project performance.
havhe social gatherings with the project team.
comparing actual performance to planeded performance.