Question: The project described by the data and network below is one that can be expedited through the expenditure of more resources on individual tasks. a.

The project described by the data and network below is one that can be expedited through the expenditure of more resources on individual tasks.

The project described by the data and network

a. Identify the critical path(s) under normal conditions

b. What is the normal project completion time?

c. What is the shortest possible project completion time?

d. Reduce the project duration, one day at a time, until the duration is 24 days. For each one-day reduction in project duration, identify what activity(s) was crashed, the project duration, and the total added cost.

The project described by the data and network

Task Normal Time (Days) 7 Minimum Time (Days) 5 Crash Cost (Dollars/day) 400 A B 9 6 300 C 10 8 500 D 8 7 600 E 12 9 400 F 11 10 700 3 3 --- G H H 3 3 1 13 10 1000 J 5 4 900 A D G B E F H Crash Decisions: Path Lengths Project Completion Total Added Cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!