Question: The project duration is: * None 17 Option 5 36 25 2. The slack time of activity D is: * 19 15 0 None 3.

The project duration is: * None 17 Option 5 36 25 2. The slack time of activity D is: * 19 15 0 None 3. The slack time of activity F is: * 2 None 0 8 4. The CP contains: * C, E, F B, C, E, F, G, H A, D, H None 5. The duration of activity A is: * 5 9 8 None 6. The variance of activity F is: * 1.7 1 2.7 None 7. The project standard deviation is: (Take one number after the comma) * 1 2.6 2.2 None 8. What is the probability to finish the project before 37 weeks: * None 62.7% 75.2% 67.3%
A network consists of the following list. Times are given in weeks. Preceding Most Pessimis Activity A B D E B A C E F Optimistic 4 2 6 6 2 3 8 5 10 8 4 12 8 14 16 6 9 F 7 H 8Step by Step Solution