Question: The project is a new 7 0 MW hydro - electric power station in Central Vietnam. The company has been asked to bid for the
The project is a new MW hydroelectric power station in Central Vietnam. The company has
been asked to bid for the engineering, procurement and construction management of the
mechanical and electrical engineering M&E works, with a contract value of approximately US$
M The project calls for the commissioning of two turbines, one to be completed in two years and
t h e other following to months later. The owner has requested that a financing
proposal is required, ie the contractor will need to find a bank o r export credit agency or finance it
in some other manner during construction. The bid will be fixed price.
The form of contract will be the client's own conditions and the governing law of the contract
will be the laws of Vietnam, al t ho ug h the contract language will be E n g l i s h and payment will
b e in US dollars. Advance payments of are available for both equipment and construction
management although the followup payments are upon receipt of major equipment and on a
monthly measure basis for construction management work.
The contract documents call for the following: $ bid bond, Performance security of of
contract price, recognition of the usual forcemajeure situations, a defects liability period of months
from handover although it will be specifically hours use for the actual turbines. There are no
retention clauses specified although liquidated damages for delay can be up to of contract value and
for performance can be up to of turbine cost.
The company would like to work with a consortium which is led by a large Japanese company. The
Japanese are known to the company but they have no previous experience of working together.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock