Question: The project is going well. There is a scope change, and, as a result, a new team is brought in to assist the existing team

The project is going well. There is a scope change, and, as a result, a new team is brought in to assist the existing team in the new scope of the project. Upon arriving, the team asks to see where the the project currently stands. What do you show them?
Group of answer choices
Work breakdown structure
Gantt chart
Network diagram
Milestone chart