Question: The project is going well until a Stakeholder requests a significant change based on a modification in the Stakeholders business process. After meeting with the

The project is going well until a Stakeholder requests a significant change based on a modification in the Stakeholders business process. After meeting with the team to determine impact it appears that the change will likely double the length of the project because of the complexity associated with the change. The change request and its impact analysis are going before the Change Control Board (CCB) for review and potential approval. What is the purpose of the Change Control Board (CCB)?

A) To work with the Change Control Manager for analyzing changes

B) To analyze changes that are requested for the project

C) To eliminate as many changes as possible on the project

D) To control change by approval of needed changes and rejection of unneeded changes to the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!