Question: The project is mostly complete. The project has a schedule variance of 3 0 0 and a cost variance of 9 0 0 . All

The project is mostly complete. The project has a schedule variance of 300 and a cost variance of 900. All quality control inspections have been completed and all have met the quality requirements. All items in the issue log have been resolved. Many of the resources have been released. The sponsor is about to call a meeting to obtain product verification when the customer notifies the project manager that they want to make a major change to the scope. The project manager should