Question: The project is not completed until: Lessons learned are completed. The project scope is completed, administrative closure is completed, and payment is received. The customer

The project is not completed until:
Lessons learned are completed.
The project scope is completed, administrative closure is completed, and payment is received.
The customer is satisfied, and final payment is received.
Formal acceptance is received, and any other requirements for project closure as stated in the contract are met.