Question: The project is using a waterfall schedule to roll out an ERP system across six departments over six months. The plan is to give each
The project is using a waterfall schedule to roll out an ERP system across six departments over six months. The plan is to give each department a one-month timebox to roll out the higher priority features within that department. Each department has a product owner who determines the priority of features. What type of development approach does this describe?