Question: The project management plan specifies that a predictive development approach has been selected to produce the project deliverables. Where in the project life cycle will

The project management plan specifies that a predictive development approach has been selected to produce the project deliverables. Where in the project life cycle will the overall project risk be the lowest? a. C b. A c. D d. B