Question: The project manager and team have created the schedule for the hospital wireless network upgrade project. The schedule includes a five-day delay for network approval
The project manager and team have created the schedule for the hospital wireless network upgrade project. The schedule includes a five-day delay for network approval before the hospital can use the upgraded network. This causes the finish date of the project to slip by five days. Which of the following best describes the delay? A schedule delay of an item on the critical path A lag from one activity to another A need to level resources The float of the activity