Question: The project manager has been asked to crash the project by four weeks. Determine which activities, in order, are to be crashed and the cost

The project manager has been asked to crash the

The project manager has been asked to crash the project by four weeks. Determine which activities, in order, are to be crashed and the cost associated with crashing for each of the four weeks. Finally, provide the total cost to crash the project by four weeks.

Activity K L N M J Q P Y Z End $90 Immediate Predecessor(s). None K K L N JM Q Q P Y, Z Normal time (weeks) 9 7 5 4 6 6 8 8 6 Crashing Costs 1st week 2nd week $820 $830 $250 $90 $600 $700 $100 $400 $450 $180 $170 $180 9 L 16 7 16 M 20 4 26 P 34 8 34 Z 40 6 OK9 20 Q 26 6 40 E 40 0 9 9 N 14 3 14 J 20 6 26 Y 34 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!