Question: the project manager has completed the project management plan and sent it to the sponsor,other take holders, and team leads for approval.Upon review one of
the project manager has completed the project management plan and sent it to the sponsor,other take holders, and team leads for approval.Upon review one of the team lead notices an important activity missing and requests that it be added to project managemt plan. What should the project manager do
advise team lead that doing the activity at this stage is gold plating
submit a change request because the team lead has already performed the impact analysis and stated the activity needs to be added
perform an impact analysis of missing activity
add missing activity to project management plan