Question: the project manager has completed the project management plan and sent it to the sponsor,other take holders, and team leads for approval.Upon review one of

the project manager has completed the project management plan and sent it to the sponsor,other take holders, and team leads for approval.Upon review one of the team lead notices an important activity missing and requests that it be added to project managemt plan. What should the project manager do?
1.advise team lead that doing the activity at this stage is gold plating
2.submit a change request because the team lead has already performed the impact analysis and stated the activity needs to be added
3.perform an impact analysis of missing activity
4.add missing activity to project management plan

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!