Question: The project manager has determined that a consultant is needed to immediately begin working on a part of the project. The work is expected to
The project manager has determined that a consultant is needed to immediately begin working on a part of the project. The work is expected to last a few weeks. What is the most appropriate contract type in this situation?
| Fixed price (FP) | ||
| Fixed price with economic price adjustments (FPEPA) | ||
| Time and material (T&M) | ||
| Cost plus fixed fee (CPFF) |