Question: The project manager is examining the tasks tasks left to complete the entire project. The remaining tasks are part of two separate paths. One path
The project manager is examining the tasks tasks left to complete the entire project. The remaining tasks are part of two separate paths. One path has zero slack left and no task that can be crashed. The other path has a slack of 5 days and two tasks that can be crashed by 3 days each. What is the maximum number of days by which the duration of this project can be reduced?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
