Question: The project manager is given a bar chart representing the statistical distribution of traffic on a stretch of road that needs work. What tool has

The project manager is given a bar chart representing the statistical distribution of traffic on a stretch of road that needs work. What tool has the project manager been handed? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. A Histogram B Pareto diagram C Fishbone diagram D Process diagram