Question: The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG. What should the project manager do first? Review and update the project schedule. Interview the other project manager to lear more details. Communicate with the client to provide the previous shutdown plan. Include the risk in the register and communicate with the stakeholders
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
