Question: The project manager is working on a new electrical wiring upgrade project for the entire office. Due to safety issues the project manager cannot move
The project manager is working on a new electrical wiring upgrade project for the entire office. Due to safety issues the project manager cannot move forward with many parts of the project without inspections and permits from the local Buildings Department. Most permits takes approximately 6 weeks to get. Where would the project manager document the opportunity the project should take if a permit comes within two weeks instead of the 6 weeks