Question: The project manager learns that one team member needs to complete a critical task that is outside of the project, resulting in a scheduling risk
The project manager learns that one team member needs to complete a critical task that is outside of the project, resulting in a scheduling risk for the project. How can the project manager eliminate this risk? SELECT THE CORRECT ANSWER Meet with the team members manager, and negotiate for an alternative time to complete the other task. Ask the team member to focus on the critical task, and obtain an additional resource from another department. Send a report to the project sponsor, documenting noncompliance from the members manager. Tell the team members manger to release the team member from outside activities until the scheduled project activity is complete