Question: The project manager, Mary, has completed the scope statement and the WBS for a small project. She has approached the sponsor about gaining approval for
The project manager, Mary, has completed the scope statement and the WBS for a small project. She has approached the sponsor about gaining approval for the scope baseline. Upon inspection, the sponsor decided the scope baseline doesnt have enough information in it What is the best action Mary can take?
Responses
Work with the team and create a WBS Dictionary
Work with the team and create a WBS Dictionary
Ask the sponsor to write the scope
Ask the sponsor to write the scope
Go back to collect requirement process
Go back to collect requirement process
Work with the team to create a project schedule and cost baseline