Question: The Project Manager reviews the programme submitted by the Contractor and realises parts of the drainage work stated in the Scope is not included and
The Project Manager reviews the programme submitted by the Contractor and realises parts of the drainage work stated in the Scope is not included and there are no time risk allowances shown. Which of the following statements best describes why the Project Manager would NOT accept the programme?
A new sports and leisure centre is being constructed using the NEC4 Engineering and Construction Contract Option B. A programme was identified in Contract Data part two by the Contractor. The interval for submitting revised programmes is 4 weeks. The starting date is 01 June. The period for reply is GO TO NEXT UNANSWERED QUESTION The Project Manager reviews the programme submitted by the Contractor and realises parts of the drainage work stated in the Scope is not two weeks. included and there are no time risk allowances shown. Which of the following statements best describes why the Project Manager would NOT accept the programme? Select ONE option C) The programme does not show the information required by the contract and it does not comply with the Scope. C) The Contractor's plans are not realistic and it does not comply with the Scope. CO) The programme does not show the information required by the contract and the Contractor's plans are not practicable. C) The Contractor's plans are not practicable and it does not comply with the Scope. C) The Contractor's plans are not practicable and it does not show the information required by the contractStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts