Question: The project manager, Sean Murphy, has concluded that he cannot meet the deadline by performing all these activities in the normal way. Therefore, Sean has
The project manager, Sean Murphy, has concluded that he cannot meet the deadline by performing all these activities in the normal way. Therefore, Sean has decided to use the CPM method of time-cost trade-offs to determine the most economical way of crashing the project to meet the deadline. He has gathered the following data for the four activities.
| Activity | Normal Time | Crash Time | Normal Cost | Crash Cost |
| A | 8 months | 5 months | 26700 | 41700 |
| B | 9 months | 7 months | 21700 | 31700 |
| C | 6 months | 4 months | 17700 | 25700 |
| D | 7 months | 4 months | 28700 | 46700 |
Use marginal cost analysis or Excel to determine the cost of completing the project in 12 months.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
