Question: The project scope stThe project scope statement and its WBS and WBS dictionary form the baseline, which is used to measure performance in meeting project
The project scope stThe project scope statement and its WBS and WBS dictionary form the baseline, which is used to measure performance in meeting project scope goals. true or falseatement and its WBS and WBS dictionary form the baseline, which is used to measure performance in meeting project scope goals