Question: The project team at Quality Construction Inc. is working on the Determine Budget process. Based on past experience, they frequently utilize a mathematical model based

The project team at Quality Construction Inc. is working on the Determine Budget process. Based on past experience, they frequently utilize a mathematical model based on cost per square foot to determine their project costs. What type of technique is theteam utilizing? (For Ref Only, Question #: PM-03559) Group of answer choices Historical information review Reserve analysis Parametric estimating Cost aggregation