Question: The project team has been asked to identify what will happen if a given IT change has a problem or causes a non - repairable

The project team has been asked to identify what will happen if a given IT change has a problem or causes a non-repairable outage. What has the project team been asked to create?
A Risk assessment
Rollback plan
C Validation checks
Automate tests