Question: The project team has been asked to include a data validation module with the software they are developing, and this will add an additional three

The project team has been asked to include a data validation module with the software they are developing, and this will add an additional three weeks to the project. This is an example of which one of the following?This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option.optionAChangeoptionBRiskoptionCIssueoptionDNone of the Above