Question: The project team has completed all duration estimates for the activities on the project and has indicated that their estimates should be with in a

The project team has completed all duration estimates for the activities on the project and has indicated that their estimates should be with in a -10 to +10% range. Where should the project team store this range?
a Schedule Management Plan
b Basis of Estimate
c Project document
d Schedule Baseline