Question: The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path. What should the
The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path. What should the project manager do in this situation? Review the critical path with the stakeholders to define next steps. Discuss the critical path issues with the purchasing department. Escalate the supplier-related issues to the sponsor for resolution. Review the work breakdown structure (WBS) with the suppliers