Question: The project team or contractor must avoid __________, which is informally making changes to the project scope without appropriate approval. Question 14 options: updating the
The project team or contractor must avoid __________, which is informally making changes to the project scope without appropriate approval. Question 14 options: updating the work breakdown structure scope creep scope change editing the project scope document