Question: The project's NPV? WACC: 10.00% Year 0 1 2 3 Cash flows -$1,000 $450 $460 $470 Group of answer choices $152.34 $156.61 $128.14 $142.37 $113.90
The project's NPV?
| WACC: | 10.00% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flows | -$1,000 | $450 | $460 | $470 |
Group of answer choices
$152.34
$156.61
$128.14
$142.37
$113.90