Question: The project's objective statement should contain: Select one: A . strengths and weaknesses of subcontractors. B . slack time and activities. C . scope, time

The project's objective statement should contain:
Select one:
A. strengths and weaknesses of subcontractors.
B. slack time and activities.
C. scope, time frame, and allocated resources.
D. activities, completion times, and incentives.