Question: The Pullman Mfg . , Inc. three - station work cell illustrated in the figure below has two machines at station 1 in parallel. (

The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel.(The product needs to go through only one of the two machines before proceeding to station2.)
Station 1
Machine A
Station 1
Machine B
Station 2
Station 3
20 min/unit
20 min/unit
2 min/unit
12 min/unit
A three-station work cell has a product that must go through one of the two machines at station 1(they are parallel) before proceeding to station 2 and then on to station 3. Both Machine A and Machine B at Station 1 take 20 minutes per unit. Station 2 takes 2 minutes per unit. Station 3 takes 12 minutes per unit.
The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station .
Part 2
a) The throughput time of the new work cell is
34 minutes (enter your response as a whole number).
Part 3
b) The bottleneck time of the new work cell is
20 minutes per unit (enter your response as a whole number).
Part 4
c) If the firm operates hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation is
180 units(enter your response as a whole number).
Part 5
d) If the firm operates hours per day, 6 days per week, the weekly capacity of the work cell without the second machine at workstation is
enter your response here units(enter your response as a whole number).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!