The quantity schedule based on Department Y's production is as follows: Actual Work Done This Month Equivalent
Fantastic news! We've Found the answer you've been seeking!
Question:
The quantity schedule based on Department Y's production is as follows:
Actual
Work Done This Month
Equivalent Production
In process, June 1
5,000
Received from Department X
20,000
Units to be accounted for
25,000
In process, June 1, finished and transferred
5,000
1/2
2,500
Received from Department X, finished and transferred
16,000
100%
16,000
In process, June 30
3,000
1/3
1,000
Normal Loss at the start
1,000
-
-
Units accounted for
25,000
19,500
The cost data are as follows:
In process, June 1
P25,210
Received from Dept. A
72,000
Factory cost, May:
Materials
39,000
Labor
19,500
Factory overhead
19,500
Per estimate, the spoiled units can be sold for P800.
What should be the unit cost for those transferred out during the month?