Question: The R&D Project : There is an R&D project at a high-tech company to be managed by Joanna. She is now under pressure from the
The R&D Project: There is an R&D project at a high-tech company to be managed by Joanna. She is now under pressure from the companys rivals to complete the project early with minimum cost. She has gathered the following information for project crashing. You will need to use such information to construct an AoA network.
| Activity | (i, j)or i->j | Activity Time (days) | Activity Cost ($1000s) | Total Allowable Crash time | Marginal Crash Cost ($1000s) | ||
| Normal | Crash | Normal | Crash | ||||
| A | (1,2) | 6 | 4 | 200 | 240 | 2 | 20 |
| B | (2,3) | 8 | 5 | 500 | 605 | 3 | 35 |
| C | (2,4) | 2 | 1 | 570 | 650 | 1 | 80 |
| D | (3,5) | 4 | 1 | 840 | 960 | 3 | 40 |
| E | (4,5) | 7 | 6 | 355 | 400 | 1 | 45 |
| F | (5,6) | 3 | 1 | 400 | 420 | 2 | 10 |
| G | (5,7) | 5 | 2 | 710 | 800 | 3 | 30 |
| Dummy 1 | (3,4) | ||||||
| Dummy 2 | (6,7) | ||||||
Question 13
Under Normal time, the latest start (LS) time of activity F is:
Select one:
a. 25
b. 24
c. 26
d. 23
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock