Question: The Red Project, Blue Project, and Green Projects are all connected to a resource pool file. The Program Manager has created a Master Project file
The Red Project, Blue Project, and Green Projects are all connected to a resource pool file. The Program Manager has created a Master Project file and Inserted all three subprojects into it. Task 5 in the Red Project must be completed before Task 7 in the Blue Project can start, so the program manager created a FS link between the two tasks in the two projects. He saved and closed all the files, including the Resource Pool file. When the Blue Project manager opens his file the next day, he notices a new gray task bar in his Gantt chart. Which of the following statements about this ghost task is false?
|
| The task no longer exists in the Red project file. |
|
| In the Predecessor column beside Task 7 in the Blue project, there is an unusual predecessor; Red Project/5FS |
|
| There is no corresponding ghost task in the Red Project indicating that there is an external successor. |
|
| If you Double Click on the ghost task in the Blue Project, it will open up the Red Project, to allow you to see the predecessor task. |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
