Question: The relationship between a predecessor activity and a successor activity is called a dependency. The successor activity starts after and is dependent on the predecessor
The relationship between a predecessor activity and a successor activity is called a dependency. The successor activity starts after and is dependent on the predecessor activity. Some activities take place concurrentlyat the same time. If they must begin at the same time, they have a startstart relationship. If the activities can start at different times but they must finish at the same time, they have a finishfinish relationship.
True
False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock