Question: The relationship between a predecessor activity and a successor activity is called a dependency. The successor activity starts after and is dependent on the predecessor

The relationship between a predecessor activity and a successor activity is called a dependency. The successor activity starts after and is dependent on the predecessor activity. Some activities take place concurrently-at the same time. If they must begin at the same time, they have a start-start relationship. If the activities can start at different times but they must finish at the same time, they have a finish-finish relationship.