Question: The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal cost Crash cost Possible number of weeks to crash

The relevant project data are given as follows.

Activity

Predecessor(s)

Normal time (weeks)

Crash time

Normal cost

Crash cost

Possible number of weeks to crash

Cost/week to expedite

A

--

7

6

$7,000

$8,000

B

A

2

1

5,000

7,000

C

A

4

3

9,000

10,200

D

B,C

5

4

3,000

4,500

E

D

2

1

2,000

3,000

F

D

4

2

4,000

7,000

G

E,F

5

4

5,000

8,000

a) Draw the AOA (Activity-On-Arc) diagram as shown in Chapter 13's Excel Worksheets.

b) Formulate the problem of finding project completion time as a LP problem. [You would only need the first 3 columns of the table and the diagram from a) to do the job!]

c) Reformulate the problem when crashing the project completion time of 3 weeks is required. That is, reformulate the problem when the project completion time is required to be shorted by 3 weeks. Obviously, crashing is based on shortening the project completion time by 3 weeks with the minimal additional cost. In order to formulate the problem, you need to fill in the blank columns of the table.

NEED EXCEL ANSWERS! DO NOT COPY AND PASTE THE ANSWER FROM OTHER POSTS!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!