Question: The reorder level for a certain widget is 64 units. The optimal order quantity is 36. The demand rate is 3 units per week and
The reorder level for a certain widget is 64 units. The optimal order quantity is 36. The demand rate is 3 units per week and the replenishment lead time is 1 weeks. The safety stock is:
Enter your value as an integer rounded up.