Question: The required maintenance workload for the next four months in a food processing plant is 5 5 0 , 4 0 0 , 3 6

The required maintenance workload for the next four months in a food processing plant is 550,
400,360, and 445 man-hours, respectively. The demand can be met by either regular time at a cost
of SR 40 per hour, overtime at a cost of SR 70 per hour or subcontract at cost of SR 95 per hour.
Regular time capacities are listed following, overtime capacity cannot exceed 25% of regular time
capacity at any month. Late maintenance (backlog) costs extra SR 15 per hour per Period.
Subcontract hours are available but can only be purchased in 120-hour contract. (This means that
you cannot use less than 100 hours of subcontract hours, increment of 100 hours).
Using the heuristic tableau method, develop the capacity plan to satisfy the required
workload
Calculate the total cost of the plan
If the subcontract hour can be used without any constraints (any limit on the number of
hours). How much that would save on the total cost of the plan?
 The required maintenance workload for the next four months in a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!